Harbour Repair Cost Problem

As we heard over the last couple of years, Cobourg’s Harbour is in urgent need of repair – that is, the harbour walls and the breakwaters need a whole lot of work.  A consultant has done the design work and the estimated cost for Phase one of the work was put in the 2022 budget and tenders issued.  Specifically, Phase one was to rehabilitate the walls on the north and east side of the marina basin as well as the fuel dock. However, all 6 bids responding to the tender were well over the amount in the budget – the budget is $5M and the lowest bid was $7M so Staff are recommending that the tender be cancelled and that… Read complete articleHarbour Repair Cost Problem